Public Jobs

Bids due in 23 days
11/5/19 2:00 pm
Rostel and Cedar Storm Drain Improvements - Central Point - Distribution
Abadan Reprographics & Imaging
Central Point, OR
Bids due in 30 days
11/12/19 1:00 pm
Cache Creek Road Slide Repairs - Distribution
Abadan Reprographics & Imaging
Ferry County, WA
Base Bid Schedule ‘A’, Lower Cache Creek, generally consists of reconstructing approximately 150 feet of roadway, including 102 C.Y. of Roadway Excavation, 148 C.Y. of imported gravel borrow, 65 tons of asphalt paving, 95 feet of Type 31 Beam Guardrail, traffic control and related site restoration. Base Bid Schedule ‘B’, Upper Cache Creek, generally consists of reconstructing approximately 175 feet of roadway, including 4,125 C.Y of Roadway Excavation, 4,853 C.Y. of imported gravel borrow, 137 tons of asphalt paving, 175 feet of Type 31 Beam Guardrail, drainage improvements, traffic control and related site restoration.
Bids due in 4 days
10/17/19 1:30 pm
Klamath Tribes Fitness Center Parking Lot and Drainage - Distribution
Abadan Reprographics & Imaging
Chiloquin, OR
Erosion and sediment control, clearing and grubbing, site demolition, tree removal, grading / site excavation and fill, approximately 1,050 L.F. of concrete curbs, 4,035 S.F. of sidewalks and garbage enclosure front slab, 22,000 S.F. of asphalt parking lot, storm drainage infrastructure and detention pond, parking lot lighting, signage, striping, and related work in conjunction with the construction of a 15,250 S.F. building. Additional site work, building, and all other utilities for the building are provided under separate contract.
Bids due in 16 days
10/29/19 2:00 pm
Septic Conversion Project Areas 1 and 2 - Irrigon - Distribution
Abadan Reprographics & Imaging
Irrigon, OR
Bids due in 18 days
10/31/19 4:00 pm
RFQ - Library Bond Projects Commissioning Agent Services - Distribution
Abadan Reprographics & Imaging
Spokane, WA
The Spokane Public Library is seeking the services of a qualified Commissioning Agent Firm to assist the Library with fundamental commissioning services at the Spokane Public Library branches. Consultant Services on behalf of the Library include, but are not limited to: provide Fundamental Commissioning as defined by the 2015 Washington State Energy Code. Commissioning shall include documentation, reports, and acceptance as specified by the WSEC. Additional enhanced commissioning services may be added for some of the projects including, but not limited to: conduct a commissioning design review, conduct verification and assurances, and develop a system manual.
Bids due in 18 days
10/31/19 5:00 pm
Ehrck Hill Dr Waterline Replacement - Distribution
Pace Engineers
Hood River, OR
The proposed work consists of furnishing all labor, equipment, tools, materials and supervision to construct approximately 160 lineal feet of 6" diameter waterline including approximately 55 lineal feet of flanged pipe to be supported along a bridge. The work will include traffic control, excavation, erosion and pollution control, disposal of excess excavation, waterline pipe, casing and casing spacers, pipe zone material, backfill, compaction, connection to existing water mains, fittings, thrust restraint, securing waterline to bridge and abutments, structural supports, pressure and bacteriological testing, dechlorination, and miscellaneous work and appurtenances.
Bids due in 8 days
10/21/19 12:00 pm
Cooke Creek Fish Screening and Passage - Distribution
Abadan Reprographics & Imaging
Ellensburg, WA
The Cooke Creek Fish Screening and Passage Project includes the installation of a concrete diversion intake structure with an 8 cubic foot per second (cfs) flat plate fish screen and fish ladder; installation of 3,920 linear feet of 10 and 12-inch PVC pipe in a shared 2,000 foot trench; installation of associated irrigation structures and connecting pipelines; removal of a concrete gravity irrigation diversion structure; and installing two rock/gravel roughened channels.
Bids due in 16 days
10/29/19 2:00 pm
Rapp Road Reservoir Construction - Phase 2 - Distribution
RH2 Engineering, Inc.
Talent, OR
This project consists of construction of a pre-stressed AWWA D110 Type 1 concrete reservoir with a storage volume of approximately 2 million-gallons, including all associated work related to earthwork, site improvements, yard piping, and reservoir mechanical, finishes, electrical and automatic control as detailed in the Plans and specification, and required by permitting agencies. Work includes, but is not limited to: soil and rock excavation; backfill and grading; subgrade preparation; construction of sitework and utilities including manholes, gravel surfaces, site fencing, and the reservoir structure including inlet, outlet, overflow, and drain piping and connections to the existing water and storm systems; and finishes for the proposed reservoir.
Bids due in 16 days
10/29/19 2:00 pm
Lawson Acres Water System Improvements - Distribution
Civil West Engineering Services, Inc
Riddle, OR
Connection to the City of Riddle; installation of a vault with a mag flow meter and a double check detector assembly, flow readout outside of the vault on a post, installing a power post as required by the power company, all electrical work to make the flow readout at a panel on the power post other than bringing power and a meter to the power post; clearing, trenching, bedding, laying pipe, tracer wire, backfilling, compaction and all other activities required to install 5155’ of 2” HDPE water pipe; installation of gate valves, blowoff and air release valves; partial demolition of the existing treatment plant; installation of a new 3000 gallon tank; connection to the existing system; testing and disinfection; all as identified within the Specifications and as shown on the Drawings.
Bidding Closed
10/10/19 11:00 am
WWCC - Student Recreation Center Bid Package #23 Re-Bid - Distribution
Abadan Reprographics & Imaging
Walla Walla, WA
Bid Package #23 Electrical Re-Bid.