Skyline Reservoir Transmission Main and Utility Improvements - Phase 1 - Distribution

This project is for replacement of the existing 14-inch steel transmission main between the reservoir located above Skyline Drive and an existing valve at the intersection of Skyline and Appleland Drive with approximately 800 feet of 16” Ductile Iron pipe and fittings. Work will include replacement of the existing valve structure with a nominal 12’ x 16’ CMU Valve Building, valving, altitude valve, re-circulation pump and appurtenances. Approximately 425 feet of 18” storm drain will replace the existing overflow pipe along Skyline Drive from the intersection of Skyline and Appleland Drive to a new air gap for the Reservoir drain.

Status

Bidding Closed

Bid Date5/7/20 11:00 am

Company & Contacts

City of Wenatchee

Jeremy Hoover   (509) 888-3212

Location

Wenatchee, WA