New MBR System and Associated Improvements - Distribution

Installation of a new treatment building to house ultrafilter (UF) membrane skids and other associated equipment, new bioreactor feed pump station, conversion of one of two existing sequencing batch reactor (SBR) tanks into a continuously-aerated bioreactor, installation of new aeration equipment, and site piping improvements. All incidental demolition, civil, structural, mechanical, electrical and controls to complete the work is included. Work also includes commissioning, start-up, training and testing of all treatment equipment.
  Specifications (click to expand/collapse)
Order this section, price will be calculated by SQFT
Order files below, price will be calculated by SQFT
Name Size
Volume 1 - Bidding Requirements 2.1 MB
Volume 2 - Contract Documents 14.4 MB
Volume 4 - Appendix to Volume 2 - Contract Documents 158.1 MB